The noise barrier project in Aalborg is in full swing and is now entering the final phases of this extensive undertaking. Another part of the project involves the delivery and installation of steel girders and arms for four bridges along the route. Here, DAV NORDIC has been responsible for reinforcing the existing bridges at four…
You are here: Home -> Cases -> Reinforcement of Bridges in Aalborg
68 tons of steel have been delivered and installed across four bridges, which have undergone extensive renovation as part of the new noise barrier project in Aalborg. These massive amounts of steel are essential for supporting the high noise barrier on the existing bridges, which previously did not require such reinforcement.
The steel girders have been custom-designed for each bridge, requiring specialized solutions. The bridge on the Ådal Motorway is designed as a pendulum structure, allowing movement along its length during summer and winter due to temperature fluctuations.
For the other three bridges, steel arms are installed to provide additional support underneath, ensuring the structures are strong enough to bear the noise barrier. The construction also includes the installation of gutters to ensure proper drainage from the bridges.
As the main contractor, DAV NORDIC has worked closely with fitters from PL Klejnsmed and crane operators from Christian Rytter to complete this project.
Careful planning and intense effort were required to finish all four bridges within three weeks while minimizing traffic disruptions as much as possible. DAV NORDIC’s project manager, Christoffer H. Jensen, has been on-site himself, assisting with the installation. DAV NORDIC’s project manager, Christoffer H. Jensen, states:
DAV NORDIC’s project manager, Christoffer H. Jensen, states: It is always exciting to see things come together. In this project, we placed extra focus on the precision of our drilling work on the underside of the bridges, as this was crucial to ensuring everything fit correctly. When it all comes together successfully, it is always a great satisfaction to be part of
It is always exciting to see things come together. In this project, we placed extra focus on the precision of our drilling work on the underside of the bridges, as this was crucial to ensuring everything fit correctly. When it all comes together successfully, it is always a great satisfaction to be part of
Having a project manager overseeing the process from start to finish, ensuring smooth execution from design to completion, is invaluable. This role is a key priority in all our projects.
The final work is expected to be completed by week 11.
Major renovation of bridge components on a 60-meter bridge in the heart of Copenhagen
In close partnership with OK a.m.b.a., DAV NORDIC has contributed to the development, production, and installation of covers for two new charging parks in Hammelev…
DAV NORDIC has responded to market demand by developing a new standard pedestrian railing, which we will keep in stock. Customers have been requesting this…
As a subcontractor to DS Flexhal, DAV NORDIC has delivered a wide range of covers for Taulov Dry Port as part of the expansion of…
DAV NORDIC has won and completed the project to deliver and install shelters with solar panels at the four fast-charging stations located at the Lillebælt…
The new district, Gartnerbyen in Odense, is a mix of culture, nature, and business, and is Odense’s new green heart. DAV NORDIC’s environmentally friendly and…
Once again, DAV NORDIC A/S has provided steel products to the construction industry. This time to SPX Flow’s warehouse and production facilities in Silkeborg. KPC…